ECV 314313 Solved Question Bank: Estimating, Costing, and Valuation

Estimating, Costing, and Valuation ECV 314313 Question Bank solutions for the MSBTE sixth-semester civil engineering students are given below.

ECV 314313 Solved Question Bank

This question bank contains chapter-wise important questions for all upcoming MSBTE examinations and unit tests.

ECV 314313 Solved Question Bank

  1. Calculate steel reinforcement in kg for 50 m3 R.C.C. work of slab, where 0.9%
    Steel reinforcement is provided.
  2. Write modes of measurement for the following: a) Brick work, b) Skirting, c)
    earthwork, d) R.C.C, e) Formwork, f) dado, g) woodwork for door and window
    frame.
  3. Define administrative approval, technical sanction, and budget provision.
  4. Describe rules for the deduction of plastering work as per IS 1200.
  5. Explain the standard format of different sheets.
  6. Enlist the checklist of items of work for the load-bearing structure and framed
    structure.
  7. Explain the role and responsibility of the estimator.
  1. Enlist types of approximate estimates.
  2. Define an approximate estimate.
  3. Write the purposes of the approximate estimate.
  4. State data is required for a detailed estimate.
  5. Define a detailed estimate and write the purposes.
  6. Enlist types of detailed estimates.
  7. What are contingencies and work-charged establishments?

Conclusion

All important questions for the Estimating, Costing, and Valuation subject are solved and listed under this question bank.